Government Of Assam Nalbari District

Ongoing Schemes

On-going Schemes as on 30-01-2019

               1. Flood Management Programme (F.M.P)

Sl No

Name of Schemes

Esstt. Amount

Ref. of Administrative Approval

Remarks

1

A/E measures to protect B/dyke on R/B of river Brahmaputra from Adabari to Kukarjan including of the dyke from Ch. 26th Km to ch. 33rd Km under F.M.P

Rs. 1366.12 L

WR(C)187/2013/47 Dt. 21-10-2014     

 

Work is in progress

  (Upto Dec’2018)

2

A/E measures to Pagladia L/B embankment from Dusutimukh to Adabari including strengthening & widening of the dyke at different reaches: At 1st Km( Kathalghopa), at 4th Km (Hablakha) & at 6th Km (Bullutpar) under F.M.P

Rs. 1444.92 L

WR(C)395/2012/45 Dt. 22-10-2014

 

Work is in progress

  (Upto Dec’2018)

3

M/E along Both Bank of river of Mora Pagladia from N.H. way to Tihu Akhara P.W.D. Road (Raising and strengthining of embankment including anti erosion works on Both bank at different reaches under F.M.P

Rs. 1800.64 L

WR(C)266/2013/47 Dt. 22-10-2014

 

Work is in progress

  (Upto Dec’2018)

 

 

2. NABARD

Sl No

Name of Schemes

Esstt. Amount

Ref. of Administrative Approval

Remarks

1

Anti-erosion measures against the bank erosion at different reaches of river Tihu  (Bhadrakuchi and its adjoining areas) under RIDF XXIII

Rs. 200.00 L

WR(C)501/2017/05 DT. 23-11-2017

 

Work is in progress

  (Upto Dec’2018)

2

Anti erosion measures to protect the R/B of B/Dyke from Adabari to Kukarjan (at Saikiapara area) from Ch. 5830m to Ch 7270m under RIDF XXIII

Rs. 325.00 L

WR(C)512/2017/05 DT. 23-11-2017

 

Work is in progress

  (Upto Dec’2018)

 

 

 

3. SDRF

Sl No

Name of Schemes

Esstt. Amount

Ref. of Administrative Approval

Remarks

1

Immediate measures to M/E along B/B of Nadla Drainage Channel from Rly. Line to its out fall at river Buradia (CLosing of miscreant cut/ breach at Ch. 6.50th Km L/B near village Purni including restoration works at breach like damage portion of the embankment) under SDRF for 2017-18

Rs. 320.00 L

RGR.(RRR)996/2017/74

Dt.05-01-2018

 

Work is in progress

(Upto Dec’2018)

2

Immediate measures to restore the flood damages to Hatipota, Soneswarjan, Pukhra on L/B of river Buradia  for 2017-18 under SDRF

Rs. 180.00 L

RGR(RRR)994/2017/72

Dt.05-01-2018

Work physically completed

3

Immediate measures to restoration the  flood damages of B/dyke  due to diversion of channel of river Brahmaputra at Kaptola  and its adjoining  area 2017-18 under SDRF

Rs. 195.00 L

RGR.(RRR).992/2017/64 

Dt. 06-01-2018

Work physically completed

4

Immediate measures to restore of flood damages at Chatemari and its adjoining area due to diversion of channel of river Brahmaputra under SDRF for 2017-18

Rs. 210.00 L

RGR.(RRR).288/2018/64

Dt. 05-05-2018

Work physically completed

5

Immediate measures to M.E along B/B of river Noona from ‘0’ point of existing embankment to its outfall (Recoupment of damaged section from Ch. 9375m to Ch. 18400m on R/B- D/S) for 2017-18 under SDRF

Rs. 175.00 L

RGR.(RRR).275/2018/52 

Dt. 26-04-2018

Work physically completed

6

Immediate measures to protect the R/B of river Pagladia from Sonkuriha to Bijulighat at 32nd Km Gangapukhuri area for the year 2017-18 under SDRF

Rs. 95.00 L

RGR.(RRR)./993/2017/64  Dt. 06-01-2018

Work physically completed

7

Immediate measures to restore the flood damages on R/B of river Noona from ‘0’ point of existing embankment to G.K. Ali (Restoration works from Ch. 0M to Ch. 3900M on R/B) for 2017-18 under SDRF

Rs. 200.00 L

RGR.(RRR).275/2018/55 

Dt. 26-04-2018

 

Work is in progress

(Upto Dec’2018)

8

Immediate measures to M.E.  along B/B of river Pagladia from G.K. Ali to N.T.  Road -Ph-I (U/S) (Bank Restoration works at 3rd Km Pub-Barsiral and at 7th Km Keherua on L/B) for 2017-18 under SDRF

Rs. 150.00 L

RGR.(RRR).275/2018/54 

Dt. 26-04-2018

 

Work is in progress

(Upto Dec’2018)