  • 1. NEW MEDICAL COLLEGE AT NALBARI under  NLCPR Scheme

    Agreement No.

     

    SMC/87/2018/28  Dated 10th Aug'2018.

    PROJECT VALUE

    A.A. value – 398.3122 Crore.

    Tender Value- 372.48 Crore

     

    Date of Commencement

    10.08.2018.

    Progress of work

    75 %

    Target of completion

    March’ 2023

     

     

    Model Residential School at Nalbari (Barkhetri) under PMJVK

    PROJECT VALUE

    3042.68 Lakh

    DATE OF Commencement

    13.10.2019

    Progress of Work

    85 %

    Target  date of completion

    Mar’ 2022

     

    Outdoor Stadium Complex at Chamata Anchalik Krira Sangha at Chamata Nalbari (Signature Scheme)

    PROJECT VALUE

    1000.00 Lakh

    DATE OF Commencement

    07.09.2019

    Progress of Work

    87 %

    Target of completion

    Feb’ 2022

     

    Block Development Office, Tihu (Signature Scheme)

    PROJECT VALUE

    10 Crore

    DATE OF Commencement

    19.06.2019

    Progress of Work

    36 %

    Target  date of completion

    Mar’ 2023

     

    ANM & GNM Nursing School at Mukalmua (Signature Scheme)

    PROJECT VALUE

    10.00 Crore

    DATE OF Commencement

    06.07.2019

    Progress of Work

    56%

    Target of completion

    Aug’ 2022

     

    Indoor Stadium & Swimming Pool at Nalbari

    The work has been withdrawn from  the contractor, Md. Munnaf Ahmed vide office letter No. 4291 dated 21.06.2021

    PROJECT VALUE

    4.04 Crore

    DATE OF Commencement

    Work withdrawn from the original contractor.

    Progress of Work

    0 %

    Allotment of balance work is under process. Work will started soon

    Target  date of completion

     

     

    RCC 2 storied Prisoners’ Ward for 120 inmates at District Jail, Nalbari

    PROJECT VALUE

    1.35 Crore

    DATE OF Commencement

    16.09.2019

    Progress of Work

    62 %

    Target of completion

    Mar’ 2022

     

    Augmentation of Govt Gurdon HS School, Nalbari under RIDF Scheme

    PROJECT VALUE

    501.32 Lakh

    Date of Commencement

    12.12.2019

    Progress of Work

    86.0 %

    Target Date of Completion

    January’2022

     

    B. Ed  College at Mugkuchi, Nalbari

    PROJECT VALUE

    776.39 Lakh

    Date of Commencement

    04.12.2019

    Progress of Work

    80 %

    Target Date of Completion

    Mar’2022

     

    Upgradation of SMK  Civil Hospital  for Set up of ICU  under Assam Critical Care Project 2020 at Nalbari

    PROJECT VALUE

    1311.34 Lakh

    DATE OF Commencement

    25.11.2020

    Progress of Work

    ICU- 100% Completed

    Residential part- Piling work is in progress. Overall 40 % completed.

    Target Date of Completion

    August’ 22

     

    Sub Regional Science Centre cum Planetarium for ASTEC under Department of Science & Technology, Assam at Nalbari

    PROJECT VALUE

    257.43 Lakh (Planetarium )

     

    291.89 Lakh (Digital planetarium projection system)

    DATE OF Commencement

    05.11.2012 (Planetarium)

    18.11.2020 (Digital Projection system)

     

    Progress of Work

    Planetarium 100 % completed. Digital Dome Installed.

    Furniture 100 % installed. Equipments  of planetarium 60% completed.

    Target Date of Completion

    Jan’ 2022

     

    Sub Regional Science Centre cum Planetarium for ASTEC under Department of Science & Technology, Assam at Nalbari

     

    PROJECT VALUE

    204.86 Lakh

    (Residential part)

    DATE OF Commencement

    27.09.2018

    Progress of Work

    Residential part  86 % completed.

    Target Date of Completion

    Jan’ 2022

     

    New Engineering College at Ghograpar, Nalbari

    PROJECT VALUE

    2466.30 Lakh

    F.W Order No.

    SMC/133/2020/30 08.06.21

    Progress of Work

    20 %

    Target Date of Completion

    Dec’ 2023

     

    Construction of 03 storied RCC I.B at Mukalmua under Barkhetri LAC in Nalbari

    PROJECT VALUE

    318.775 Lakh

    Date of Commencement

    03.02.2021

    Progress of Work

    18 % completed. Work upto plinth level completed. GF column casting is in progress.

    Target Date of Completion

    August’ 2022

     

    Proposed construction of Inspection Bunglow (I.B) at Ghograpar in Nalbari District

    PROJECT VALUE

    368.99 Lakh

    Work order Date

    24.09.2021

    Progress of Work

    8  %

    Target Date of Completion

    Dec’2022

     

    Establishment of Govt. Law College in 10 places of Assam

    (at Tihu in Nalbari District)

    PROJECT VALUE

    1474.00 Lakh

    Work order Date

    02.02.2021

    Progress of Work

    15 %

    Target Date of Completion

    Mar’2023

     

    Construction of proposed Office cum I.B  for PWD Nalbari Rural Road Division , Nalbari

    PROJECT VALUE

    274.515 Lakh

    Work order Date

    09.06.2021

    Progress of Work

    Work not yet started

    Target Date of Completion

     

    Bottleneck:  Work could not be started as the site has been changed and proposed to construct at the proposed Integrated Deputy Commissioner Office, Nalbari.